Project Type. | Procurement No | Procurement Approach |
Procurement Name
|
Project Sector | Agency | Awarded Party | Awarded Amount | Awarded Duration | Awarded Date | Summary |
---|---|---|---|---|---|---|---|---|---|---|
Works | NT/2023/SSP- 045 | Direct Selection | Design and Build of Ha. Filladhoo Harbour Road | Road | Ministry of National Planning, Housing and Infrastructure | Road Development Corporation Limited (RDC) | MVR 29,860,450.63 | 240 Days | 25/05/2023 | View Download |
Works | NT/2023/SSP- 044 | Direct Selection | Design and Build of N. Kendhikolhudhoo Major Roads | Road | Ministry of National Planning, Housing and Infrastructure | Road Development Corporation Limited (RDC) | MVR 90,894,554.10 | 540 Days | 25/05/2023 | View Download |
Works | NT/2023/SSP- 040 | Direct Selection | Design and Build of N. Maalhendhoo Shore Protection | Shore Protection | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 34,933,925.16 | 270 Days | 30/04/2023 | View Download |
Works | NT/2023/SSP- 043 | Direct Selection | Design and Build of Harbour Upgrade Works at F.Nilandhoo | Harbour / Channel Works | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 66,695,528.52 | 510 Days | 18/05/2023 | View Download |
Works | NT/2023/SSP- 042 | Direct Selection | Design and Build of Shore Protection Barrier Island (3rd) at HA. Hoarafushi | Shore Protection | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 10,300,705.20 | 180 Days | 18/05/2023 | View Download |
Works | NT/2023/SSP- 041 | Direct Selection | R.Dhuvaafaru Harbour Upgrade | Harbour / Channel Works | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 42,114,781.44 | 450 Days | 14/03/2023 | View Download |
Works | NT/2023/SSP- 039 | Direct Selection | Coastal Protection- Adh. Dhigurah | Coastal Protection | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 12,684,642.51 | 150 Days | 25/12/2023 | View Download |
Works | NT/2023/SSP- 035 | Direct Selection | R. Kinolhas Shore Protection | Reclamation | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 12,368,484.00 | 180 Days | 11/04/2023 | View Download |
Works | NT/2023/SSP- 037 | Direct Selection | Design and Build of R. Alifushi Major Road | Road | Ministry of National Planning, Housing and Infrastructure | Road Development Corporation Limited (RDC) | MVR 90,956,112.97 | 540 Days | 11/04/2023 | View Download |
Works | NT/2023/SSP- 038 | Direct Selection | Design and Build of F. Magoodhoo Airport | Airport | Ministry of National Planning, Housing and Infrastructure | Maldives Transport and Contracting Company Plc (MTCC) | MVR 50,233,868.69 | 200 Days | 11/04/2023 | View Download |